So, the foundations are done. That's the first major stage of the build out of the way and we can really start to get cracking on with things.
Next stage - we get 10 tonnes of sand delivered and around half of the bricks and blocks (not all of them due to space constraints). Then bump the bricks out ready to start laying them. Yep there's no easy jobs at the start.... during the hottest part of the build

.
Just bumped out enough bricks and blocks to get to DPC (damp proof course) level.

- Some bricks and blocks in place ready for laying.
- S1050329.jpg (276.03 KiB) Viewed 315 times
....Then start laying some bricks and blocks!

The final outside ground level will be a few inches below the top of the brickwork level in this picture. Yep still lots of groundwork to go yet. but that ain't the half of it! The internal floor level will be flush with the top of the brickwork in this pic. But that's too much volume to fill completely with concrete as it would cost a fortune.

- Brick and blockwork to DPC level
- S1050334.jpg (252.18 KiB) Viewed 315 times
While we're at it, here's a few piccies of the rear of the plot showing the remaining earth that will need to be moved by hand later on. Also shown is the soakaway - a fairly large pit, about 4 x 6 ft and about 5ft deep. This is where any visiting planning officers will be buried. Hehe not really. It will be filled with hardcore (rubble - not the other kind) and milk crates creating a substantial amount of airspace below the ground. The surface rainwater from the roof of the house will run into here to drain away, meaning I wont have to pay extra for it to run into the main sewage infrastructure

.
You can also see my fairly large lean-to storage shed (well kind of a shed) at the rear of the property. Loads of storage space for junk hehe. The back wall of the lean-to marks my rear site boundary. Also note the trenches down the left and right sides for the services (water, electric, gas, sewerage).

- piles, trenches, lean-to etc
- S1050337.jpg (304.15 KiB) Viewed 316 times

- Grav....er... Soakaway
- S1050338.jpg (269.76 KiB) Viewed 316 times
Not sure why but I have a small gap in the photo's here. The next stage was to break up about 6-7 tonnes of hardcore (rubble from that pile shown in some of the previous photos) with a sledgehammer and spread it around on the ground on the oversite (inside the brickwork). This was the hardcore that came from the site itself, mostly from the foundations of the greenhouses and dug out of the ground. This was nowhere near enough though so I had a 10 tonne delivery of pre-smashed hardcore delivered which I wheelbarrowed from round the front of the garage (seen in another piccie earlier) as that was the only place it could be dropped. Still wasn't quite enough so then another 5 tonnes turned up.... which was too much argh! Not to worry though because it will be used for my paths and some will be thrown in the soakaway. Then the hardcore is all levelled out and compacted down firmly, after which it is covered with about 2 inches of sand to mask the sharp edges of the rubble beneath. This is then levelled, smoothed and further compacted forming a solid base for the insulation and concrete to sit on. At this stage there is about 20 tonnes of material inside the oversite!
You can partially see this in the next picture:

- For some reason, the only piccie I have of the "hard work" beneath the concrete hehe
- DSC00455.jpg (210.96 KiB) Viewed 316 times
tbc.....